MINUTES

SPECIAL MEETING OF THE

GREEN BAY HOUSING AUTHORITY

Thursday, November 3, 2009

1424 Admiral Court, Second Floor Reading Room

Green Bay, Wisconsin 54303

1:30 p.m.

 

 

MEMBERS: D. Dolan-Wallace-Chair, D. Piton, H. Genunzio, D. Slater.

MEMBERS EXCUSED:  None.

MEMBERS ABSENT: W. VandeCastle-Vice-Chair.

OTHERS PRESENT: R. Strong, R. Hallet, A. Monday, D. Johnson.

 

OLD BUSINESS:

 

  1. Review and possible action on the plans for the Mason Manor expansion project.

 

D. Dolan Wallace explained that potential revisions to the existing plan were discussed by himself, R. Strong, W. VandeCastle, T. Lesperance, D. Johnson, and Dan Piton in the previous meeting on October 28th, 2009 .  The changing of the new heating system from electric to a small multiple-boiler system was considered, in addition to the possibility of removing the stairwell from the current project.

 

D. Dolan Wallace stated that the additional stairwell would provide better emergency services in the event of a fire.  One alternative would be to leave room, or a knock-out panel to allow for the installation of a stairwell at a later date.  Eliminating the stairs from this project would save about $200,000. 

 

D. Dolan Wallace explained that under current regulations, if more than 50% of the building is remodeled, the addition of the stairs would be legally required.  D. Dolan Wallace indicated that if that much remodeling were done, adding two stairwells would probably be required or recommended.  He did clarify that this remodeling percentage was cumulative, so smaller projects could add up to 50% over the course of small projects.  This code has been in effect since March of last year, so that is when this accumulation would have begun.

 

D. Piton discussed the addition of a sprinkler system, or the possibility of consolidating some of the smaller units into larger ones. 

 

D. Johnson from AGL indicated that the exclusion of the stairs would allow for more storage space in the current plan, and that the footprint of the building would remain the same through either alternative.  The alternate plan would still allow for another roof access point.  This access point could be safer than the existing access through the use of a ship’s ladder.  D. Johnson also pointed out that the 2nd floor door would be replaced with windows, and the 20-foot limit for corridor length would still be met. 

 

D. Dolan-Wallace indicated that the 2nd option would require a roof or canopy over the access area.

 

D. Johnson explained the third option: A plan that looks at using the space without any accommodations for a future stairwell.  The last option would reduce the square footage of the addition’s footprint from 1623 to approximately 1260.  This option provides everything the other plans do, but it would be difficult to add a stairwell later.

 

D. Piton indicated that the third plan could lead to a serious problem in the future, if a stairwell is needed or desired.

 

D. Dolan-Wallace indicated the importance of sprinkler systems and changes in code, especially in terms of elderly housing.  In many cases, the project could count on being grandfathered through any changes, but that it is possible for residential buildings to have mandatory code changes.

 

D. Piton asked how much of the project funds were from federal sources.  R. Strong stated that $431,000- $451,000 were ARRA funds, and that both plans would use that full amount (The amount of ARRA funds are $341,467).  The ARRA funds need to be obligated by March 17th.

 

D. Piton asked about the financial difference between the plans, excluding the third option presented. 

 

D. Johnson replied that the cost for the original plan is about $1.5 million, the layout that would accommodate a future stair addition would cost $1.3 million, and the plan that does not allow for the addition of stairs would cost $1.2 million.  The final savings of leaving the stairs out, would provide only about $80,000 in savings when accounting for knock-out panels and planning.

 

D. Dolan-Wallace indicated that the only compelling reason to put stairs in is for rescue services, and that the addition of sprinkler systems should be considered.

 

D. Johnson stated that the fire pump would have to be replaced, and this would cost $20,000-$40,000.  Installing the actual sprinklers would require access to the apartments, and replacing some of the ceilings.  Building-wide sprinklers could be estimated to cost about $2.25 per square foot.  With the addition of the pump, this would run $250,000.  The changes to the ceilings would drive the project cost up to $450,000-$500,000.  The generator might also require an upgrade, which could cost an addition $80,000. 

 

D. Johnson stated that he spoke with John Fredericks, the heating engineer, about the installation of four compact, 110,000 BTU boilers. J. Fredericks had stated that this was not feasible because of the venting requirements. Also, the condensation is acidic, and could cause brick discolorations or damage, and could create dangerous icicles.  There isn’t adequate water and gas lines to this area currently, and the extra maintenance of four extra units should be considered.  The installation of smaller units would provide little to no savings over one central location.  It was also indicated that with this system, the condensation points would need to be staggered to prevent large icicle build-up.

 

 

D. Johnson estimated that the installation of a new boiler to serve all eight floors would cost $60,000 to install and pipe, while tapping into the existing boilers would cost $35,000.  Tapping into the existing boilers is not feasible, however, This cost could escalate to $50,000-$60,000 with remodeling and labor to get the lines through the units.

 

D. Johnson stated that the utilities cost of the electric heating system would be $2,400-$2,500 more per year than a gas system.  While the installation cost of electric system wasn’t available during the meeting, D. Johnson stated that the savings might not pay off before the effective life of the current boiler system expires.

 

No changes were proposed to the current plan of using electric heat.

 

D. Dolan-Wallace asked if the window system at the end of each hallway is something that could be reused if a stair-less system were used.  D. Johnson stated that the re-use of the window system is something that could be looked at.  The addition of this stairwell might lead to it becoming a more common entrance, and sidewalks may need to be added.

 

D. Dolan-Wallace pointed out that the stairwell would need cleaning, painting, and other maintenance.  He then stated that he was uncertain about how much of a fire sprinkler addition might be considered remodeling.  He felt that a strong argument could be made that the addition of a sprinkler system would not be considered remodeling. 

 

R. Strong inquired about collecting bids for the project both with stairs and without stairs.

 

D. Dolan-Wallace inquired about the doors in the plan, and whether they would be included in the alarm system.  He then stated that receiving alternate bids for a plan with and without stairs is probably the best option.  The fire suppression would be left as is under both plans.

 

A motion was made by D. Piton to accept the plans as drawn, with the exception of receiving alternate bids for the plan without a stairwell.

 

Motion seconded by H. Genunzio.

 

Motion carried unanimously by voice vote.

 

D. Johnson stated that the plan might need some slight alterations, but it should be finalized two weeks from now.  The results will be brought in for the meeting on December 17th.  The board will be notified if this timeline cannot be met.

 

D. Dolan-Wallace asked about the fire-rating of the doors and windows in the plan without a stairwell, and D. Johnson stated that these would be removed from the alternate plan as appropriate.

 

D. Johnson mentioned the use of a new generation of elevator, and the size of elevator was planned around accommodating moving and emergency personnel, with a capacity of 5,000 pounds.

 

A motion was made by D. Piton and seconded by H. Gununzio to adjourn the meeting at 2:15 p.m.  Motion carried.

 

:jml